Levels, Sublevels and Development Layouts
A development layout is the connected arrangement of underground openings that makes exploration, construction and production possible. Levels and sublevels organize that arrangement vertically, while drives, crosscuts and connections establish routes through it. Their design must resolve where work can occur, how it can be supplied and when each area becomes usable. A set of evenly spaced lines on a section is only a geometric starting point.
Levels, Sublevels and Functional Naming
A level is a system of approximately horizontal workings at an operating horizon. A sublevel is a secondary or intermediate horizon associated with extraction. A drift generally follows the strike of the deposit; a crosscut crosses it or connects workings. A raise is an upward-developed steep opening between horizons. These names describe different aspects of an excavation: elevation, orientation or connection.[1]
A main level may provide enduring access, haulage and services to several production areas. Sublevels may provide more local access for drilling or extraction. These are functional distinctions: the design should state what each horizon does instead of assuming that its name establishes its capacity or service life. Shaft, decline and adit access can each connect into level workings; the label “level” does not determine the surface access method.
Level names also need a documented reference. A number may identify an elevation, depth below a reference point or simply a historical operating horizon. Drawings should therefore provide actual coordinates and elevations, the applicable datum, and unique opening identifiers. “Upper sublevel” is adequate conversational shorthand only while everyone is referring to the same production block.
Selecting Elevations, Spacing and Position
The first layout decisions concern the mineralized geometry and the chosen extraction method. Identify where drilling, extraction, travel and services need access, then test whether a proposed set of horizons can provide it. Orebody bends, branches, changes in thickness and interruptions by faults may justify local departures from a regular vertical arrangement.
For sublevel stoping, Castro and Pineda identify orebody geometry, drilling technology and capital cost as influences on sublevel spacing. Their discussion distinguishes drill and auxiliary levels from the draw level. Consequently, an interval selected to reduce development must still provide workable access to the planned rock volume and an effective route for broken material. Their gravity-flow research also cautions against treating the in-situ arrangement of grades as an unchanged extraction sequence after blasting and drawing.[2]
Spacing should be compared through complete alternatives. A wider interval can remove some access development but change drilling requirements and the production volume dependent on each horizon. A closer interval can increase the number of access points while adding excavation, services and future inspection obligations. The comparison needs the same production target, geological assumptions and definition of readiness; otherwise an apparent development saving may simply omit necessary work.[2]
Footwall means the rock beneath an inclined deposit. Penn State's illustrative layout places permanent access on that side to reduce exposure to damage propagating through the hanging wall as mining proceeds. This explains one reason for considering footwall access; it does not establish that every footwall alignment is suitable.[1]
Compare possible alignments against structures, rock quality, anticipated excavation effects, connection lengths and the periods for which access must remain available. An alternative through ore or another wall position needs the same assessment, including whether subsequent extraction would consume the route.
Production drives warrant particular care. Villaescusa describes how their position can affect stope boundaries: an existing or poorly located drive can undercut a wall and contribute to falloff. In wider open stopes, separate drill drives may provide access for perimeter drilling and reinforcement. Thus, minimizing the number of drives is subordinate to the functions and ground conditions they must accommodate.[3]
Connecting Workings in Three Dimensions
A plan view can conceal both missing connections and conflicts. Check levels together in sections and a three-dimensional model, tracing complete journeys from the main access to the workplace and onward to the material destination. For every connection, identify its function, opening geometry, direction of movement and period of availability.
In the sublevel-stoping system discussed by Copland and Nehring, extraction access and drilling access are developed before the production sequence. They also explain that the access and haulage arrangement affects when production areas become available. Transport may involve successive handling stages rather than a single direct route.[4]
A practical connectivity review asks:
- Where does development waste go before the permanent ore-handling system is available?
- Can people, supplies and equipment reach the workplace while production haulage is operating?
- Which connections are intended for travel, material transfer, ventilation or services, and which functions may coexist?
- Does extracting or filling one area interrupt a route needed by another?
- How will equipment be installed, maintained and eventually removed?
A raise shown between two levels is not automatically a travel route, orepass or return airway: its designed function and equipment determine its use. Likewise, two lines intersecting on a plan do not prove that workings connect at compatible elevations. Connection details should resolve these ambiguities before their availability is assumed in the schedule.
Vertical separation also involves ground interaction. Slaker and colleagues examined multiple-level limestone mines and explained how interburden properties, thickness and relative pillar positions affect stress transfer between levels. Their work concerns stone-mining conditions; it does not establish a universal interval for metal mines. It does demonstrate why an additional horizon must be assessed together with the excavations above and below it, rather than checked as an isolated level.[5]
Converting Development into Production Readiness
A production schedule needs dates for usable access, not merely completed excavation lengths. A heading can reach its planned endpoint while ground support, connections, services or operating checks remain incomplete. For planning purposes, separate physical advance from the release of an area for its intended activity.
The following distinction provides a useful review structure; the actual acceptance criteria belong to the project design and operating arrangements.
| Development milestone | Question before crediting availability |
|---|---|
| Access reaches the area | Is the route usable by the intended people and equipment? |
| Working openings are excavated | Are their surveyed geometry and ground condition acceptable for the next task? |
| Connections are completed | Do material, air and service routes work through the required network? |
| Services are installed | Have the necessary systems been checked for the intended duty? |
| Production preparation is complete | Are the method-specific prerequisites and interfaces satisfied? |
Work backward from the required production date to identify milestone dates and predecessor activities, then check whether a forward schedule can achieve them with the available crews, equipment and services. A target date is not evidence that access can be ready. Additional development faces offer little scheduling flexibility if they all depend on one unfinished connection. Conversely, a deliberately prepared alternative area may preserve options when its access and services can operate independently. Compare that option with the cost of developing and maintaining it early.
Ventilation, Services and Changing Layouts
The Mandela Mining Precinct ventilation guideline lists mine layout, opening dimensions and the production profile among design inputs, and includes development ventilation in its design criteria.[6] An engineering implication is to check intermediate layouts and incomplete connections as well as the final arrangement, because the available air paths change as development proceeds.
Apply the same staging discipline to water, power, communications and material supply. The design review should ask how each service reaches a new heading, how its route changes when connections open and which installations must move before extraction advances. Reserve the required space at junctions and working areas, and assign responsibility for interfaces. A service shown schematically through a production opening needs an explicit replacement or removal milestone if that opening will later be consumed.
Survey Feedback and Layout Revision
Survey control provides the spatial reference for comparing proposed and actual workings. Western Australia's Mines survey - code of practice, second edition (2011), addresses connections between surface and underground surveys, datum relationships and preservation of survey records. For layout review, these relationships allow proposed connections and surveyed workings to be compared within a common spatial reference.[7]
Keep design alignments, surveyed excavations and interpreted geological surfaces distinguishable. An as-built update should show where an opening exists; it should not silently redefine the geological interpretation or mark an unfinished connection as operational. Record the design revision associated with each released work package so that deviations can be assessed against the intended geometry.
Consider a qualitative change: development exposes a fault closer to the planned connection than the model indicated. Rerouting the crosscut may be appropriate, but moving its endpoint alone leaves unresolved questions. The revised connection could change drilling access, the ground assessment, service lengths and the date at which a ventilation circuit becomes available. The response is to review these dependent functions and update the development sequence together. Survey and geological observations then provide the evidence for deciding whether the revised arrangement remains suitable as excavation proceeds.
References
- Pennsylvania State University. Module 10: Underground Mining. Location: Sections 10.2.1 and 10.2.3, Deposit and Spatial Terms; Excavation Terms; discussion of Figure 10.2.1. Accessed: 2026-10-27. ↩1 ↩2
- R. Castro; M. Pineda. The role of gravity flow in the design and planning of large sublevel stopes. 2015. Location: Current design practices for sublevel stoping; Laboratory experiments; Experiment 2. Accessed: 2026-10-27. ↩1 ↩2
- Ernesto Villaescusa. Geotechnical Design for Sublevel Open Stoping. 2014. Location: Sections 1.3, 1.4.1 and 1.4.6, printed pp. 3-8 and 16 (publisher preview). ISBN: 978-1-4822-1189-4. Accessed: 2026-10-27. ↩
- T. Copland; M. Nehring. Integrated optimization of stope boundary selection and scheduling for sublevel stoping operations. 2016. Location: Mine layout and design; Production. DOI: 10.17159/2411-9717/2016/v116n12a7. Accessed: 2026-10-27. ↩
- Brent Slaker; Michael Murphy; Gamal Rashed; Vasu Gangrade; Mark Van Dyke; Todd Minoski; Kristin Floyd. Monitoring of Multiple-level Stress Interaction at Two Underground Limestone Mines. 2020-11-23. Location: Introduction, printed pp. 623-624. DOI: 10.1007/s42461-020-00345-z. Accessed: 2026-10-27. ↩
- E. Preis; L. Meyer. Guideline: Ventilation Engineering. Location: Sections 2.1-2.3 and 2.8, printed pp. 20-22. ISBN: 978-0-7988-5655-3. Accessed: 2026-10-27. ↩
- Department of Mines and Petroleum. Mines survey - code of practice. 2011. Edition: Second edition. Location: Sections 2.2 and 2.6-2.8, printed pp. 4-6. ISBN: 978-1-921163-70-8. Accessed: 2026-10-27. ↩