Geology, Exploration & Mine Surveying

Geology describes and interprets rocks, structures and mineralisation. Exploration searches for deposits and tests geological interpretations through planned investigation.[1] Mine surveying locates observations, excavations and infrastructure within a shared spatial framework.[2]

The disciplines exchange information throughout a project. Geological interpretation guides the next investigation; exploration supplies new evidence; surveying locates it relative to the mine and its designs. A useful result preserves the difference between what has been observed, what has been inferred and what remains uncertain.

Geological and Spatial Understanding

Lithology identifies rock or sediment types; weathering and alteration describe changes that can affect engineering behaviour. Structures such as faults, folds and joints help explain continuity and potential instability. Mineralisation describes the distribution of minerals of interest, while the body's geometry describes its position, thickness, orientation and extent. Together, these properties inform the arrangement and dimensions of excavations.[3]

For a rock excavation, discontinuity orientation relative to the opening can govern potential block release; in a sand deposit, material strength may be more relevant than a joint network. Engineering geology connects these observations to ground behaviour.[3] Hydrogeology links groundwater conditions to engineering decisions: pressure can affect stability, expected inflows inform dewatering and pumping, and chemistry influences water reuse and treatment. These relationships matter in both surface and underground mines.[4]

Exploration and Investigation

Investigation starts with a question: whether mineralisation continues, where a contact lies, or which conditions may affect an excavation. Existing records are checked before selecting new work. Mapping, geochemical surveys and drilling examine different aspects of the geological interpretation. Geophysics measures physical properties; responses may reflect mineralisation itself or associated rocks and minerals. An anomaly therefore requires geological interpretation.[1] Results may require revising the interpretation.

Data adequacy depends on spatial coverage as well as the number and quality of observations.[4] Work concentrated around easy access or visible mineralisation may leave other areas poorly constrained. An engineering implication is to investigate ground around proposed openings and infrastructure, including material with little mineral value.

Drill-hole collars and downhole trajectories position logged intervals in three dimensions. A collar location alone does not establish where a deviated hole intersected a geological feature.[1] A downhole intersection length is not automatically the true thickness of a mineralised body; interpreting thickness requires the orientation of both the hole and the body.[4]

Sampling, Analysis and Data Quality

A sample is intended to represent a specified interval or volume. Representativeness depends on sampling design, core or sample recovery, splitting and preparation. Procedures and analytical methods must suit the material and intended measurements. Sample identifiers should connect locations and intervals with handling records, preparation methods and laboratory certificates, so the origin and treatment of a result can be reconstructed.[1]

Quality control combines certified reference materials, blanks, duplicates and independent laboratory checks to assess analytical accuracy and precision.[1] Documented acceptance criteria, review of results and investigation of failures make these controls useful.[4]

Good laboratory performance cannot establish that the selected samples adequately represent unsampled ground. Adding holes without correcting systematic identification or preparation problems can repeat the same errors. These are different failure mechanisms, so the response should match the diagnosed problem. Retaining the evidence and recording corrections allows later reviewers to distinguish a changed interpretation from a changed input.

Interpretation and Geological Models

Observed data include logged contacts, measured orientations, survey positions and analytical results. These observations also carry measurement and recording uncertainty. Correlating contacts between holes, extending a mineralised zone or assigning values to unsampled volumes requires interpretation. Models should retain links to the original evidence and document the assumptions used to bridge gaps.[4]

Scale determines which questions a model can address. A regional framework may guide investigation while omitting features important to an individual excavation. Confidence depends on data reliability, distribution, geological complexity and modelling choices. A finely subdivided display does not create supporting observations.[5]

Estimation domains group material judged to share relevant geological and statistical characteristics. Their boundaries, the interpolation method and the volume represented by an estimate affect the result. Model resolution must suit the evidence and intended mining use; smoothing can conceal local variation.[4]

Validation asks whether the model is consistent with observations and suitable for its purpose. It does not prove a unique geological interpretation. Alternative plausible geometries merit consideration where they would change an engineering decision.[5]

Mine Surveying and Spatial Control

Survey control provides reference positions from which measurements and engineering locations are derived. Stable marks, checked observations and network adjustment allow different surveys to be compared. Surface and underground control must be connected, with relationships between local grids and external reference systems documented.[2]

Coordinates need an identified horizontal reference system, units and height datum. An apparent displacement between datasets may arise from incompatible references rather than ground movement. Before combining datasets, verify their coordinate and height references and document any necessary transformations and checks. The same numerical elevation does not guarantee the same physical level.[2]

Setting out transfers design positions and levels into the field. Subsequent surveys measure the geometry achieved, allowing comparison with design and preparation of current drawings. This applies to open-pit features and underground development, with methods selected for each setting. Accuracy and checking requirements depend on the engineering task and applicable local requirements.[6][7]

Survey records preserve original measurements and the changes incorporated into current mine plans. Inherited plans may have uncertain positions or extents of old workings; current plans should identify those limitations.[2] The practical handoff also requires geological work: newly exposed contacts need logging and correlation before the geological model is revised. An updated excavation surface and an updated interpretation answer different questions.

Uncertainty and Engineering Use

An engineering consequence of these distinctions is that uncertainty belongs to the feature or decision it affects. A well-surveyed borehole can still leave the contact between holes uncertain. Likewise, confidence in grade does not demonstrate knowledge of groundwater connectivity. Investigation priorities follow from what could alter a decision and the consequence of being wrong.

Under the Canadian CIM Definition Standards (2014), a Mineral Resource requires “reasonable prospects for eventual economic extraction”; geological identification alone is insufficient. A Mineral Reserve is an economically mineable portion of Measured or Indicated Mineral Resources, supported by pre-feasibility or feasibility studies and application of Modifying Factors, including technical, economic, environmental and legal considerations. The economic conclusion applies to the conditions assessed at the reporting date. Greater geological confidence alone does not establish reserve status.[8]

During mining, compare new exposures, measured workings and observed ground or water behaviour with predictions. A mismatch may require checking data, changing an interpretation or collecting targeted evidence before modifying the design.[3] For example, a newly mapped fault may prompt review of mineralised continuity, opening geometry and possible water connections; correcting its surveyed position addresses only one part of that review.

References

  1. CIM Mineral Resource and Mineral Reserve Committee. CIM Mineral Exploration Best Practice Guidelines. 2018-11-23. Location: Sections 2.1.1–2.1.1.1 (pp. 2–3), 2.3–2.6.1 (pp. 5–8), 2.6.3–2.6.4 (p. 9), 2.6.6 (p. 10) and 2.7–2.7.4 (pp. 11–12); printed page numbers. Accessed: 2026-10-26. ↩1 ↩2 ↩3 ↩4 ↩5
  2. Department of Mines and Petroleum. Mines survey: Code of practice. 2011. Edition: Second edition. Location: Sections 1.3–1.4 (p. 2), 2.2–2.8 (pp. 4–6), 3.2–3.4 (p. 8), 3.7 (p. 9) and 4.1–4.2 (pp. 12–14); printed page numbers. ISBN: 9781921163708. Accessed: 2026-10-26. ↩1 ↩2 ↩3 ↩4
  3. Department of Mines, Industry Regulation and Safety. Ground control management in Western Australian mining operations – guideline. 2019. Location: Section 3.1, printed pp. 4–9; Figure 3.1, printed p. 5. ISBN: 9781922149701. Accessed: 2026-10-26. ↩1 ↩2 ↩3
  4. CIM Mineral Resource & Mineral Reserve Committee. CIM Estimation of Mineral Resources & Mineral Reserves Best Practice Guidelines. 2019-11-29. Location: Sections 4.1–4.2 (pp. 6–8), 4.4–4.5 (pp. 9–10), 5.1–5.5 (pp. 10–15), 6.7 (p. 20), 6.9–6.10.1 (pp. 21–22) and 7.4–7.4.2 (pp. 36–37); printed page numbers. Accessed: 2026-10-26. ↩1 ↩2 ↩3 ↩4 ↩5 ↩6
  5. David Entwisle. 3D geological modelling at the British Geological Survey (BGS). 2019. Location: Presentation slides on metadata (PDF pp. 28–29), model scope (PDF p. 32) and uncertainty/confidence (PDF pp. 67–68, 71 and 73–74). Accessed: 2026-10-26. ↩1 ↩2
  6. CPPSSI6021 Conduct open pit mine surveys. Edition: Release 1. Location: Application, p. 2; Elements and Performance Criteria 2.2–2.6, p. 3. Report number: CPPSSI6021. Accessed: 2026-10-26. ↩
  7. CPPSSI6033 Conduct underground mine surveys. Edition: Release 1. Location: Application, p. 2; Elements and Performance Criteria 2.3 and 3.2–3.8, pp. 3–4. Report number: CPPSSI6033. Accessed: 2026-10-26. ↩
  8. CIM Standing Committee on Reserve Definitions. CIM Definition Standards for Mineral Resources & Mineral Reserves. 2014. Location: Foreword, printed p. 2; Mineral Resource, printed p. 4; Modifying Factors and Mineral Reserve, printed p. 6. Accessed: 2026-10-26. ↩